If you are seeing this message, you are likely using an older browser to view this site. This website's content is fully accessible to all browsers, however the web site will look much better and your experience will be much more enjoyable if you upgrade your browser to a more current version. Please visit this web site to upgrade your browser.

DEQ.utah.gov - Utah Department of Environmental Quality

 

Pollution Control Facilities and Sales Tax Exemption

Division of Water Quality Contact:

Steve Palmer (801) 538-6073
or e-mail srpalmer@utah.gov

General Background and Guidance

Certain pollution-control facilities are exempt from sales tax. These facilities are defined as any land, structure, building, installation, excavation, machinery, equipment, device, etc., if the primary purpose of the construction or installation is to prevent, control, or reduce air or water pollution. The following information outlines rules and procedures used by the state to determine if a facility qualifies for the exemption.

Guidance for "Primary Purpose"

Test used by DAQ

Procedures For Tax Commission Consultation Between the Utah State Tax Commission and Department of Environmental Quality For Certification of Air and Water Pollution Control Facilities
Scope of Tax Commission Consultation

Utah Code 19-2-125 provides that the Air Quality and Water Quality Boards consult with the Utah State Tax Commission (USTC) prior to certifying a pollution control facility. USTC will not duplicate the detailed analysis of Department of Environmental Quality (DEQ) engineers. It is also the Tax Commission's intent to not delay the certification process. Therefore, these procedures provide that USTC be made aware, early in the process, what facilities are being considered for pollution control certification. Early awareness provides opportunities for input during the approval process rather than waiting until after DEQ has made a determination and perhaps causing unnecessary delays in certification. USTC awareness of facilities under consideration and of approximate control facility costs are helpful in assuring compliance with state tax laws.

In summary, DEQ will generally make two formal contacts with USTC--the first at the time of original application to DEQ and the second, when the application is complete. The assumption is that the initial application is often not complete and DEQ requests additional information. It is intended that should substantial changes occur between the initial and final applications, DEQ will inform USTC. It is not necessary that USTC be copied for every piece of correspondence and communication between DEQ and the applicant.

Procedures
  1. When DEQ receives an application for certification, DEQ will forward the application cover sheet to the USTC Operations Division Deputy Director. The purpose of the cover sheet is to provide USTC with initial information needed for their consulting purposes. The cover sheet will contain, at minimum, the following items:
    • Name of company
    • Location of pollution control facility(ies)
    • Each pollution control facility's estimated or actual total costs
    • Contract date or construction/installation start date and estimated completion date, if project not completed
    • Contractor(s) of the pollution control facility(ies)
  2. The Deputy Director will provide cover sheet copies to a committee composed of one representative each from the Commission, Operations, Audit, and Property Tax. This committee will meet once a month or as needed to discuss pending applications. Based upon such discussion, USTC will raise any concerns with DEQ prior to the completed application submission (see 3 below).
  3. Often, DEQ determines the initial applications are incomplete and requests the applicant to provide additional information. When all information has been received by DEQ and the application is considered complete, DEQ will send a complete application to the Operations Division Deputy Director. If a determination of certifiability on a part of the original application is made by DEQ prior to an application being complete, e.g., the applicant is resubmitting an application form to include only a limited number of items upon which there are no questions by DEQ concerning certifiability, DEQ will forward the new cover sheet to USTC at that time.
  4. The special committee of Tax Commission people will review the updated/complete application. If there are concerns or questions with any part of the application or proposed certification, USTC will contact the appropriate division in DEQ within 30 days to discuss their questions or concerns before a final certification is issued by DEQ. Regardless of USTC's position on the certification, USTC will provide a written response to DEQ within the 30 days. The Operations Division Deputy Director will draft the response for the USTC Executive Director's approval.
  5. If USTC's response is needed more quickly than allowing a full 30 days or if more review time is needed, DEQ and USTC will negotiate a response time.
  6. If for any reason a determination of non-certifiability is changed by DEQ after notification to USTC, then DEQ will again notify USTC to allow any further comment by USTC.
  7. If a DEQ determination of non-certifiability is formally appealed by the applicant to the Air Quality Board or the Water Quality Board, DEQ will notify USTC that an appeal is pending and that the initial determination by DEQ could be changed by the Board. DEQ will notify USTC of any appeal hearings scheduled before their Boards.
  8. When a certification is issued by DEQ to an applicant, it will include instructions (supplied by USTC) on what information and/or documentation they must provide to USTC when applying for the sales tax refund.